Construction of a double-girder footbridge with tubular cladding. Assembled on the ground and installed by crane. Length: 67 m divided into 3 spans.
Footbridge over the Bourges
Type of work
- bridge and footbridge
Summary
1
2
Type of service
- Architectural metalwork
- Flooring
- Lighting
- Metal framing
Stakeholder(s)
- Gagne
Project owner
Famille Missionnaire de Notre Dame
Project manager
SARL d'Architecture Hubert Tallon
Architect
SARL d'Architecture Hubert Tallon
Location
Saint Pierre de Colombier (07)
Country
France
Date of delivery
2019-2020
Time of work
14 months
Amount of work
1 200 000 €
Market
Separate lots
Steel tonnage
82 tonnes