Construction of a postal sorting centre on a 17,000 m² site.
The building comprises a 2,400 m² industrial section dedicated to the sorting process and a 400 m² office section.
Chronopost
Type of work
- Industry
Summary
1
1
Type of service
- General contractor
Stakeholder(s)
- Briand Construction
Project owner
CHRONOPOST
Project manager
ATELIER REYNALD EUGENE
Location
Ferrières en Brie (77)
Country
France
Date of delivery
2014
Amount of the operation
1 219 470 €
Surface built
4650 m²
Steel tonnage
63 tonnes
m3 Concrete
1800 m3