Villeneuve Maintenance Technicentre

Type of work
  • Industry
Summary
Image
Image
Image
Image
Image
Image
1
6

Construction of a train maintenance building, including structural work, metalwork, roofing and cladding, attic space (2,222 m²) and walkways (2,222 m²).

Supply and installation of railings along the platforms/pits of the extension to the Villeneuve Maintenance Technicentre.

Type of service
  • Architectural metalwork
  • Metal framing
Stakeholder(s)
  • Alphametal
  • Gagne

Project owner

SNCF Mobilité

Project manager

SNCF Réseau

Location

Villeneuve st Georges (94)

Country

France

Date of delivery

2019

Time of work

4 months

Surface built

6 654 m²

Market

Subcontractor

Steel tonnage

971 tonnes